Investment
Phase 1: Foundation, Steel Structure, & Roof
Schedule
Jun 2011: Materials ordered & delivered to site.
Feb 2012: Construction begins but encountered problems with installation of helical piers
Mar 2012: Change in plan for half of foundation, using concrete piers at columns, will use helical piers at floor support
Jun 2012: Foundation installed
Dec 2012: Building to be errected
Jan 2012: Roofing to be installed
| Budget | ||
| Foundation: | $57470.00 | * |
| Steelworks: | $50,294.00 | ** |
| Roofing: | $24,423.00 | |
| Shipping: | $17,500.00 | |
| Project Management & Travel: | $28.194.00 | |
| Taxes & Site Security: | $5,128.00 | |
| Donated Services: | $7,500.00 | |
| Total Phase 1: | $173,009.00 |
* Foundation requires specific technology known as helical piers to accommodate local soil conditions.
**Steelworks to be manufactured and shipped from Uganda. No supplier available in Southern Sudan.
Phase 2: Floors & Walls
Schedule
Nov 2013: Excavation for Latrines / begin walls
April 2014: Finish walls and latrines – school structure complete and weather tight
May 2014: Interior fittings and furniture installed. Solar lighting and computer lab installed
June 2014: School completed
TOTAL LABOR & SERVICES:$195,009.00*
| Phase 2 Budget | ||
| Flooring: | $52,000.00 | |
| Walls: | $45,000.00 | |
| Doors & Windows | $15,000.00 | |
| Project Management & Travel | $20,000.00 | |
| Shipping & Misc. | $10,000.00 | |
| Total Phase 2: | $152,000.00 | |
| TOTAL MATERIAL COST: | $130,000.00 | |
| TOTAL PROJECT ESTIMATE: | $325,009.00 |
* US standard for labor and services is estimated at 55% of the total project cost. Our project is 60% due to the increase cost of shipping and travel.
** Building Season is South Sudan is only 4 months due to the 8 month rainy season which makes it impossible to ship supplies on the washed out roads.